I was recently asked a very interesting question from a user of MS Project Server 2007:
“How can I assign a resource to a task that I’ve allotted 10 days to complete, but have the team member think they have to complete it the first 5 days of the task’s duration?”
Pretty sneaky, but still an excellent question! What this person essentially needed to know was how to add a buffer to a task. The goal is to allow the work on a critical task to slip for a short period of time without impacting any of its successor tasks. Of course once the buffer is used up, then subsequent tasks in the schedule may be impacted.
Fortunately, I’ve come across this one before so I had an answer ready. If you need to add task or project buffers to your schedule, read on!
How to create a buffer:
To describe how to add a buffer, I’ll use a simple example of adding a task buffer although the same technique can be used to add a buffer to a project.
For the task in need of a buffer, a new task will be inserted which will represent the buffer. It is probably a good idea to insert this buffer task right after the detail task so that we can easily keep our eye on it. This buffer task should have the same predecessor and successor relationships as the detail task. In addition, the buffer task will have a Finish to Finish (FF) relationship with the detail task.
For example:
Let’s say I have a detail task “Code Module” that is dependent on completion of the “Design Module” activity. I also have a “Test Module” task that cannot start until coding is completed. The Duration for all of these tasks is 5 days each. I inserted these three tasks into my project schedule, input the Durations, and created the relationships. Here is the result:
Now, I need to add the buffer for my Code Module task. I will insert a new task below my Code Module activity called Code Module Buffer. I will also create the links as described above. We need to have the predecessor relationship in place so that if the Design Module task slips, both the Code Module activity and its associated buffer will adjust accordingly. Having the Finish-to-Finish relationship in place between the detail task and the buffer task ensures that once our buffer is used up, our subsequent Start and Finish dates for successor tasks will adjust accordingly. This last part also requires that the successor relationships for the Code Module activity apply to the buffer task as well.
Whew! That seems like a lot of links, but it’s really pretty simple as you can see here:
You may have noticed that I have not yet entered a Duration value, or buffer amount, for my buffer task. This of course is the next step! Determining what the buffer amount should be is a topic best saved for another blog post, so for now let’s just assume that I would like to have 5 days of buffer. Since my Code Module task has a Duration value of 5 days, the total Duration of my buffer needs to be 10 days. This allows 5 days for the actual coding activity and 5 days for the buffer, as shown here:
After I change my duration for the buffer task, you can see my Finish date for that task has pushed out by 5 days. I now have my 5 day buffer! In addition, my dependent tasks have also adjusted to accommodate the buffer.
Managing the Buffer:
We now have our buffer set up and it’s time to begin executing our project. The first question we need to ask is, what happens if the resource takes more than the 5 days to complete the task? For example, what if our Duration grows from 5 days to 9 days? Well, let’s take look:
The convenient Change Highlighting feature of MS Project 2007 (isn’t it great!?) shows that the only thing impacted by this slippage is the Finish date of the Code Module activity. Because we have our built-in buffer, the scheduled dates for the subsequent activities have not been impacted. Yet.
Now, what happens when the Duration for the Code Module activity grows beyond the allotted buffer amount? What if it takes 12 days? I bet you can guess the answer, but let’s take a look anyway:
That’s right! Because we used up our buffer, and then some, the Start and Finish dates for our successor tasks have shifted. In this basic example, all of our tasks are on the critical path, so our project finish date has also been delayed.
There is one more important question to ask regarding managing our buffer. That is, what happens if the resource completes the work without using up the buffer? Because we have built this buffer into our schedule, the Start of any successor tasks is now unnecessarily delayed. This one will require some active schedule management on your part but the solution is still pretty easy! Once the task is complete, you can “close the buffer” by simply setting the Duration for the buffer task equal to the Actual Duration of the detail task and then marking it as 100% complete.
To demonstrate this example, I have assumed that it took our hard working resource only 7 days to complete the Code Module task. After entering in the Actual Duration, Duration, and %Complete values, here is what we have:
Good news! Our Test Module activity can now begin earlier than originally scheduled because we didn’t use our entire buffer. Again, because all of our tasks are on the critical path we are now on track to finish our project earlier than planned. Our stakeholders will definitely be happy!
"Our stakeholders will definitely be happy". If you put buffer for 40 days, then stakeholder will be even more happier because you finish your project additional 30 days before schedule, isn't it?
Posted by: eques | November 12, 2007 at 06:55 AM
Projjex.com is a great new site that does a fabulous job of project management. It’s completely browser-based, really easy to use, and has a free version. Cool videos too - I love it!
Posted by: Leah | April 05, 2008 at 01:04 PM
Projjex.com is a great new site that does a fabulous job of collaboration. It’s completely browser-based, really easy to use, and has a free version. Cool videos too - I love it!
Posted by: Leah | April 05, 2008 at 01:36 PM
In a field where there are many project management software products, MS Project, or Microsoft Project, is the most well-known. It is essential in most environments for project managers and/or project team members to have at least a basic level of skill with Microsoft Project.
Posted by: pdumsproject | August 03, 2009 at 07:47 AM
what happens if the resource completes the work without using up the buffer?
Instead of making a manual entry for the duration of the buffer you can automate the process.
you simply copy with a link the actual end date of the activity code to the actiual end date of the buffer . This way as soon as you enter an actual end date for the activity the actual end date of the buffer is automaticaly fixed to that date.
Posted by: Jean PAradis | September 24, 2009 at 10:21 AM
I purchased Microsoft Streets and Trips 2005 on CD a couple of years ago and would
like to upgrade to Streets & Trips 2007. My laptop does NOT have a DVD, only a CD
and I cannot find the software on CD. Can anyone tell me if there is
somewhere that I can purchase it on CD. Failing that, if I purchase
the program on
DVD, will it work to I have a computer shop or someone with an
auxilary DVD load the DVD onto my computer or does the DVD have to
stay in the computer for the program to work?
Posted by: generic viagra | April 22, 2010 at 09:39 AM
Thanks for the excellent tutorial, I think that it is qutie hard to solve this kind of dubts because you know what it is like but you don't know how to do it or how it is called.
Posted by: Generic Viagra | March 23, 2011 at 09:52 AM
I’m just trying to clarify slot size calculations and how to roll it up to figuring out the number of requires servers in an HA cluster.
Posted by: cheap jerseys | June 25, 2011 at 03:48 AM
Why not possess the post posted for the facebook? This can be ideal.
Posted by: Official NFL Jerseys | July 12, 2011 at 12:30 AM
The project looks promising on so many levels.
Posted by: Tory Burch Shoes | July 15, 2011 at 01:49 AM
This buffer task should have the same predecessor and successor relationships as the detail task. In addition, the buffer task will have a Finish to Finish (FF) relationship with the detail task.
Posted by: louboutin shoes | August 01, 2011 at 01:33 AM
I’m just trying to clarify slot size calculations and how to roll it up to figuring out the number of requires servers in an HA cluster.
http://www.jerseyscheapchina.com/ cheap Packers Jersey
http://www.wholesalechinacenter.com/ wholesale Browns Jersey
http://www.underjersey.com/ wholesale falcons jersey
http://www.cheapusajersey.com/ wholesale lions jersey
http://www.chinacheapjerseyswholesale.com/ wholesale Green Bay Packers Jersey
http://www.chinawholesalecheapjerseys.com/ wholesale Denver Broncos Jersey
Posted by: Official Kobe Bryant Jersey | August 11, 2011 at 04:25 AM
The most important concept to remember is that Project Server is only a component on a SharePoint Farm, so when you migrate a Project Server you are installing new services on your http://www.cheapjordanretroshoes.com SharePoint environment. With this in mind, it is easier to understand how to distribute the services on the new environment because the existing
Posted by: Jordan Shoes | August 24, 2011 at 05:15 AM
This buffer task should have the same predecessor and successor relationships as the detail task. In addition, the buffer task will have a Finish to Finish (FF) relationship with the detail task.
Posted by: lacoste shoes women | August 24, 2011 at 05:23 AM
Well,OK.I have to say,what a wonderful blog it is.thank you for your sharing so good articles in the website.I like it very much.It is very interesting in it.Look forward to reading so good articles in the website.
Posted by: rs2shopping | September 06, 2011 at 03:13 AM
If you need to add task or project buffers to your schedule, read on!
Posted by: borse louis vuitton | September 17, 2011 at 03:06 AM
Functional managers are often equally frustrated with the lack of visibility into project schedules and demands. They are surprised to find their resources spending time on unauthorized work for projects that are not in line with company or departmental objectives.
Posted by: Moncler Outlet | October 10, 2011 at 05:41 AM
Your post is an excellent example,I keep on reading this attractive blog.
Posted by: Detroit Tigers Jersey | October 11, 2011 at 05:57 AM
Last time, I talked about Project Tracking through Milestone Management, and how to set up a structure in your project plans where you could track a defined set of milestones.
Posted by: Moncler Outlet | October 26, 2011 at 04:36 AM
I adore how we are able to all communicate our f
Posted by: Timberland Boots | December 13, 2011 at 11:05 PM
http://www.officialpatriotsonline.com/deion-branch-jersey
Posted by: Steve Smith Authentic Jersey | January 06, 2012 at 12:12 AM
I call it proper management.
Posted by: revenue cycle | January 26, 2012 at 06:22 AM